Kfar Masaryk BWRO

Quick summary

Client

Israeli water authority

Location

Kibbutz Kfar Msaryk, Israel

Capacity

6,000,000 m³/year
16,400 m³/day

Scope of works

- 16 years BOT project
- Complete engineering services
- Detailed design
- Process engineering
- Civil works
- Construction
- Commissioning
- Full O&M services

Overview

GES is a leading partner in the consortium, responsible for the design, construction and operation of Kfar Masaryk desalination plant, which is currently the only desalination plant in the North Israel. Kfar Masaryk desalination plant receives raw saline water from two different wells and supplies more than 15,000 m³/day of high quality potable water to the local grid.

Solution

Besides the process design and equipment manufacturing, GES was responsible for all civil, mechanical and electrical works on site.  During the design several advanced process design features were implementing, granting the project with reliable performance and cost effectiveness.

Currently , the desalination plant is operated by the experienced in-house team.

Features

  • Low footprint
  • Minimized power consumption
  • Energy recovery  by turbocharger units
  • Inline chlorination by electrolysis
  • Efficient re-mineralization process